Special Weather basket construction contingency plans

As encounter some unusual weather conditions, the operator should correctly handle the basket, reasonably and effectively respond to unusual weather conditions arise, ensuring the operator basket, basket safety equipment and supplies, the emergency measures as follows:
First, the typhoon season winds or weather emergency measures:
1, during the typhoon season winds and construction, must arrange personnel responsible for listening to and watching the weather forecast and windy weather at any time to report unusual circumstances.
2, when the work of the gusts greater than 8.3 m / s (equivalent to five wind), must stop using.
3, when the work of the gusts greater than 8.3 m / sec. Or after a typhoon, should be prepared in advance, the basket must be parked to the ground, and with a rope fixed to the basket.
4, each time work, should be parked gondola to the ground, and cut off the power.
Second, thunderstorms and waterproof emergency measures:
1, thunderstorms should stop using electric basket, and the basket parked to the ground, and take measures fixed.
2, during the thunderstorm season construction, mine water should be prepared to work; in particular, electrical equipment and cables should be a comprehensive inspection, if damaged insulation or leakage phenomenon exists.
3, before each work, should hoist and electric control box waterproof treatment is necessary to prevent water from entering the night, set the guide does not work properly or the occurrence of leakage accidents.
4. If it is found Appliances inflow of rain or rain soaked, they should stop using the device immediately and notify service personnel to confirm qualified before use.
Third, other special weather conditions emergency measures:
1. When the temperature is above 40 ℃ weather, should cease operations, should be parked gondola to the ground, and cut off the power.
2, when the ambient relative humidity greater than 90% (25 ℃), should stop the job and cut off the power.
3. In case of snow or fog appears, stop work.